Today was the final prep day for the 3rd section of driveway. Grates had to be installed before the concrete gets poured tomorrow. The first set of pictures below show the top part of the driveway which will be done at a later time.
It's been a long time coming, but we finally made it to the last concrete pour of this driveway. The last section took 16 cubic metres of concrete and we proved today that a concrete truck with 5 cubic metres of concrete can reverse up the driveway with no trouble at all. This says a lot about the strength and planning of such a driveway given the slope. It also has greater meaning for the house build - all footings and slabs will have easy access for the trucks in the future! Pete, Will and Clynton were on board today to finish the final section, which looks great - well done guys.