Peter Ford Blocklayers are building the retaining wall at breakneck speed and doing a great job. The wall looks exactly as I imagined it to at this stage. Of course we need to smooth the tops of the wall once the block laying is complete, but all going to plan.
Today was a big success, the rest of the wall was cut by allcoast saw cutting and the drainage behind the wall was installed. This consists of an aggy pipe with aggregate stones on top and finally soil as the final layer. Peter was able to use the stockpile of soil on site and ordered exactly the right amount of drainage gravel (10 meters) for the job. Well done Pete!