Ford Blocklaying aren't mucking around, they are almost done with the wall and the curves that have been created are looking spectacular. Pete also ordered a chilli bin as we need to cart the debris left over from the wall construction this coming week. There's quite a bit to do once the wall has been built, installing the aggy pipe behind the wall and waterproofing it for starters. Let's hope the weather holds up.
Today was a big success, the rest of the wall was cut by allcoast saw cutting and the drainage behind the wall was installed. This consists of an aggy pipe with aggregate stones on top and finally soil as the final layer. Peter was able to use the stockpile of soil on site and ordered exactly the right amount of drainage gravel (10 meters) for the job. Well done Pete!